Protection&Control Transmission Line Protection Busbar Protection Transformer Protection Circuit Breaker Protection Generator Protection Feeder Protection Capacitor Protection Motor Protection Transfer & Synchronization Arc Protection
Digital Substation PCS-221S Merging Unit PCS-221 Merging Unit PCS-222 Circuit Breaker Controller PCS-9250 AC Electronic CT/VT
Automation PCS-9700 Automation System PCS-9700 HMI Software PCS-9705 Bay Control Unit PCS-9705S Bay Control Unit PCS-9799 Station Manager PCS-9799S Station Manager PCS-9710 Remote Terminal Unit PCS-9710S Remote Terminal Unit PCS-9794 Protocol Converter PCS-9785 Satellite-Synchronized Clock PCS-9882 Ethernet Switch PCS-9882Rx DIN Rail Managed Ethernet Switch PCS-9882XD Managed Ethernet Switch PCS-9884 Managed Ethernet Switch Supporting HSR and PRP MUX-2M/64 Communication Interface
Phasor Measurement PCS-997S Fault Line Locator PCS-996S-G Phasor Data Concentrator PCS-996 Phasor Measurement Unit
Disturbance Fault Recording PCS-996RC Disturbance Fault Recorder PCS-996R Disturbance Fault Recorder PCS-986 Disturbance Fault Recorder PCS-9013 DFR Management System
Stability Control System PCS-992 Power Stability Control System PCS-993 Out-of-Step Controller PCS-994 Frequency & Voltage Controller PCS-994S Frequency and Voltage Controller
Power Grid Monitoring and Control PCS-9000 Energy Management System PCS-9000 Distribution Management System
Configuration Tool PCS-Torch MOT Tool PCS-Studio Configuration Tool PCS-Explorer IED Configuration & Debugging Tool PCS-SCD Configuration Tool PCS-COMM Configuration & Debugging Tool
Accessories MD1501 Series Auxiliary Relays MD1701 Series Test Blocks MD1701S Test Block
FACTS PCS-9580 Static Var Compensator PCS-9583 Static Synchronous Compensator PCS-9570 Series Compensation PCS-9590 DC De-Icer PCS-9578 Controllable Shunt Reactor PCS-8200 Unified Power Flow Controller PCS-9571 Fault Current Limiter PCS-9564A Dynamic Voltage Restorer PCS-9569 Shore Power System
HVDC PCS-8600 UHVDC Converter Valve System PCS-9550 LCC-HVDC Control and Protection System PCS-8100 VSC-HVDC IGBT Valve PCS-9520 VSC-HVDC Control and Protection System PCS-9510 Cooling System PCS-8300 High-voltage DC Circuit Breaker PCS-9250 DC Electronic CT/VT
PV & Wind Power Grid-Connection PCS-9700 Renewable Energy SCADA PCS-9726 Generation Management Unit PCS-9700F Power Forecast System PCS-9700R AGC/AVC
Battery Energy Storage System PCS-9567MV-10000 Medium Voltage Skid PCS-9567MV-7000 Medium Voltage Skid PCS-9567MV-5000 Medium Voltage Skid PCS-9567MV-3500 Medium Voltage Skid PCS-9567-2500 Twin Power Conversion Systems PCS-9567-2500 電力変換システム PCS-9567-1750 Power Conversion System PCS-9567-1750 電力変換システム PCS-9567 Power Conversion System Vulnerability Disclosure Policy パワーコンディショナー脆弱性開示ポリシー
Microgrid PCS-9617MG Microgrid Controller
Static Frequency Converter PCS-9575 Static Frequency Converter
Protection,Automation&Control DMS EMS Stability Control & WAMS Digital Substation
HVDC & FACTS De-Icing Unified Power Flow Controller (UPFC) Series Compensation Static Synchronous Compensator(STATCOM) Static Var Compensator (SVC) LCC-HVDC Transmission VSC-HVDC Transmission
Renewable & Microgrid Energy Storage System Microgrid PV Generation SFC
Power Generation Pumped Storage Power Plant Nuclear Power Plant Hydro Power Plant Thermal Power Plant
Transmission System AC Transmission LCC-HVDC Transmission VSC-HVDC Transmission
Distribution System Distribution Network
Industrial Consumer Urban Track Traffic Electrified Railway Oil & Petrochemical Metals & Mining
Recently, Electricite Du Cambodge (EDC) has successfully completed a series of tests including regional power grid black start and off-grid/grid-connected operation, using the 100 MW/200 MWh GS12 grid-forming energy storage power station as the startup power source.
All key functional verifications were accomplished in one go, covering black start, regional grid restoration, isolated grid operation, start-up and grid connection of hydro and thermal power units, as well as switching operation between off-grid and grid-connected modes with the main power grid. The whole process ran steadily, fully achieving the preset test objectives.
NR Electric provided an all-round grid-forming integrated solution equipped with full sets of core equipment such as grid-forming PCS, EMS and PMS, together with system simulation test support for this project.
During the test, the grid-forming energy storage system maintained full-process grid-forming voltage source characteristics. Multiple large-capacity main transformer impact tests of 75 MW and 100 MW were carried out. A total of 182.8 kilometers of 230kV high-voltage transmission lines were put into operation, restoring the operation of four 230kV substations and 40 MW regional load. It also successfully supported the start-up and grid connection of large-capacity hydropower and thermal power units at the terminal, forming a stably operated regional power grid integrating power sources, loads and energy storage.
Meanwhile, three synchronous grid-connection tests and two off-grid disconnection tests between the energy storage system and the main grid were completed. The system maintained stable voltage and frequency support throughout the whole process.
NR Electric’s NR-ISGrid ideal synchronous power source grid-forming energy storage technology plays a vital role in improving power grid resilience, enhancing system stability and supporting rapid grid restoration.

Energy Management System Control System
This regional power grid black start test fully verifies the maturity and advancement of NR Electric’s NR-ISGrid ideal synchronous power source grid-forming technology.
NR Electric will continue to drive innovation and engineering application of grid-forming energy storage, and contribute more NR solutions to the global new generation power systems.